New Shelter Update
Great progress is being made on the construction of the new shelter on East White Hills Road.
October 2025 Update - Most of the exterior work on the building has been completed, and it’s full steam ahead on interior work. The roof is water tight, with windows and siding due to be installed by late October. Our interior walls are up, with HVAC and other systems being installed.
November 2025 Update - Much progress has been made since our last site visit in October. The windows and siding are being installed, the parking lot has been paved, and the walls are going up inside. We are now in the progress of getting power to the site.
Plans are to open the facility next summer (2026). But we still have much to do before we can open. Over the fall and through the winter we expect the plumbing, electrical, flooring and finishes to be completed.

Construction Progress
November 2025

October 2025

July 2025

June 2025